Loose screed uncovered
The existing screed could only be properly inspected once the tiles had been removed. It was loose and unsuitable as a reliable base for the new finish.
A complete floor replacement in Northwood, delivered while the homeowners were away. Beneath the old tiles, we uncovered a loose, poor-quality screed that needed replacing before we could lay the new black-and-white floor.
The homeowners arranged the work around their holiday. The goal was to have the existing floor replaced and the bathroom returned to full working order before they arrived back. That meant organising the removal, rebuilding the floor base and refitting the bathroom in a tightly planned programme.
The complication appeared only after the existing floor tiles were taken up. The screed beneath was loose and of poor quality. Covering it with a new finish would not have been appropriate, so the defective material had to be removed. This unexpected preparation was treated as an additional variation.
Use the sliders to compare the existing large-checkerboard floor with the completed small-format pattern.

BEFOREAFTERThe photographs show the same bathroom from approximately comparable viewpoints, not digitally matched camera positions.
The previous larger checkerboard tiles were replaced by a finer black-and-white layout. A geometric border now frames the entrance.

BEFOREAFTERCarefully refitting the bathroom fittings reveals the completed smaller-format floor, aligned through the main room.

BEFOREAFTERThe replacement pattern continues around the bath and towards the shower, replacing the original large-format checkerboard tiles.
The hidden weakness beneath the old tiles shaped the programme and the installation approach.
The existing screed could only be properly inspected once the tiles had been removed. It was loose and unsuitable as a reliable base for the new finish.
Removing the failed screed and forming a new approximately 30 mm screed was extra work not visible at the initial stage. This was recorded as a variation and required additional time.
Once the replacement screed was prepared, a tile mat was installed before laying the black-and-white tiles and the patterned border. The floor was then grouted.
The fittings were put back in place and the room returned to use. The programme was arranged around the clients' holiday so they came home to a completed bathroom floor.
Every image below comes from the photographs supplied for this Northwood project. No stock photos, simulated images or Dropbox-hosted images are used.
The larger black-and-white tiles before removal, with the existing bath, vanity and shower in place.
After careful removal, the existing screed was found to be loose. Removing and replacing the failed substrate added unforeseen work to the programme.
A smaller black-and-white checkerboard with a geometric entrance border, grouted and ready for daily use.
Tell us about your existing floor, desired tile pattern and any concerns about what may be underneath.
Customer feedback from Google Reviews. Tap any review to open the Master Tiling Ltd Google listing and read reviews there.
All reviews on Google ↗Share your plans and a few photos. We'll discuss the next steps.